Thursday, 14 July 2022

Power Upgrade

It's a bit of dėjavu with Daniel's crew here today to get the data lines run throughout. Then there is mounting the new TV on the wall, moving the router and phone lines to a new location and the inevitable extra 16 double power points we are getting installed.  Two days work in that lot.  We have not looked in the roof cavity until today so our due diligence was a bit lacking when they found that the reflective tube linking the skylight to the roof window had collapsed onto the upper ceiling.  No wonder it was a bit darker in the laundry.  We have three months to report defects for a fix.  The installations are going well as I can see a nicely mounted TV even though the swivel arm is a bit stiff and these TVs seem to be getting thinner and more fragile with time.


note DE logo on team uniforms


No comments:

Post a Comment